Schedule

Please find estimated schedules below:

For project updates or questions related to the the Plumbing Replacement Project, please do not hesitate to contact our office at (619) 507-9466 or your project’s dedicated Operations Manager, Greyson Connelly, at greyson@cmpcorp.net.

  • Pre-Construction Prep Month: COMPLETE
  • Kitchen Stack Waste Mains: COMPLETE
  • Domestic Water Main Installation: COMPLETE
  • Domestic Water Main Installation: East Tower  November 15th, 2023 – March 8th, 2024 (In process)
  • Commercial Waste Mains:  COMPLETE
  • West Tower Units:  March 18th, 2024 – October 1st, 2024
  • East Tower Units:  September 26th, 2024 – April 1st, 2025
  • Close Out:  April 1st, 2025 – May 31st, 2025

Note: Further details and schedules will be released as required for the project. Please click the link below for all available tower schedule impacting residential units. 